Industrial dismantling follows an order: isolate and drain utilities and lines, dismantle piping and instrumentation, remove the equipment with planned lifting, and finally the structure. JEMP dismantles complete plants, including piping, structure and lifting, from its base in Cabreúva/SP.
Stages
- Survey: inventory, layout, access routes, lifting points, maximum floor load.
- Release: lines drained and cleaned, power and utilities locked out by the plant owner.
- Piping and instrumentation: cutting or unflanging, identification of the parts to be reused.
- Equipment: lifting with a mobile crane or overhead crane, according to the rigging plan.
- Structure: platforms, mezzanines and supports.
- Transport: flatbed trailer, with tie-down and, when needed, escort.
What the plant owner prepares
- Equipment empty, clean and with any remaining contents declared.
- Lockout of power and utilities.